Practice Free SAFe-SPC Exam Online Questions
Question #31
What is the target percentage for the Program Predictability Measure?
- A . <50%
- B . 50-75%
- C . 80-100%
- D . 100%
- E . None of the above.
Correct Answer: C
Question #32
WSJF is recommended for prioritizing the Team Backlog.
- A . True
- B . False
Correct Answer: B
Question #33
What statement applies to Iteration Planning in SAFe?
- A . Iteration Planning is required in every Iteration to enable fast learning cycles.
- B . Teams that have no dependencies may choose not to do Iteration Planning once they have planned the PI.
- C . Component teams require Iteration Planning in every Iteration, while Feature teams may or may not, based on dependencies.
- D . Iteration Planning is required for all Iterations except for the first one, since there’s nothing to cause a change in the PI plan yet.
- E . When the teams define acceptance criteria during PI Planning, Iteration Planning is not strictly required during the PI.
Correct Answer: A
Question #34
What contributes to establishing trust in SAFe?
- A . Decentralization of control.
- B . Transparency.
- C . Reporting.
- D . U-curve optimization.
- E . Servant leadership.
Correct Answer: B
Question #35
(Select 2) What factors favor centralized decision-making?
- A . Infrequent decisions.
- B . Need for fast decision-making.
- C . Economies of scale
- D . Appropriate authority level of the decision maker.
- E . High cost of delay
Correct Answer: A, C
Question #36
ARTs that consist only of Feature teams do not require an Architectural Runway.
- A . True
- B . False
Correct Answer: B