Question #81
When an Increment is considered valuable? (choose the best two answers)
- A . It reduce long-term operational costs.
- B . It is delivered before the deadline
- C . It includes all the features that the Product Owner expects
- D . It increases customer satisfaction
Correct Answer: A,D
A,D
Explanation:
The satisfaction of the client is valuable and significant. A way to bring value is also to reduce operational costs (it means that the product has a minimal or no technical debt issue, the tech quality is high), which consequently reduces the total cost of ownership. All increments are delivered on time because there is a time-box for the Sprints. Before the end of the Sprint, there is no need to have all the Sprint Backlog items completed.
"It includes all the features that the Product Owner expects" : having all the features that the Product Owner expects does not mean the Increment is valuable. The Product Owner needs to release the Increment, to test the hypothesis whether the Increment is valuable or not.
"It is delivered before the deadline": if the Developers finish all the Product Backlog Items before the Sprint ends, then they should talk to the Product Owner to pull more works. In this case, the Product Backlog Items are overestimated.
A,D
Explanation:
The satisfaction of the client is valuable and significant. A way to bring value is also to reduce operational costs (it means that the product has a minimal or no technical debt issue, the tech quality is high), which consequently reduces the total cost of ownership. All increments are delivered on time because there is a time-box for the Sprints. Before the end of the Sprint, there is no need to have all the Sprint Backlog items completed.
"It includes all the features that the Product Owner expects" : having all the features that the Product Owner expects does not mean the Increment is valuable. The Product Owner needs to release the Increment, to test the hypothesis whether the Increment is valuable or not.
"It is delivered before the deadline": if the Developers finish all the Product Backlog Items before the Sprint ends, then they should talk to the Product Owner to pull more works. In this case, the Product Backlog Items are overestimated.