Practice Free PSPO-I Exam Online Questions
Question #51
Which of the following are true about the length of the Sprint? (choose the best answer)
- A . The length of the Sprint should be proportional to the work that is done in between Sprints.
- B . All Sprints must be one month or less.
- C . Sprint length is determined during Sprint Planning, and should hold the time it will take to build the planned features in the upcoming Sprint, but does not include time for any testing.
- D . Sprint length is determined during Sprint Planning, and should be long enough to make sure the Scrum Team can deliver what is to be accomplished in the upcoming Sprint
Correct Answer: B
B
Explanation:
The Scrum Guide states that “Sprints are the heart of Scrum where ideas are turned into value”. It also states that “Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint”. Furthermore, it states that “Sprints are limited to one calendar month. When a Sprint’s horizon is too long the definition of what is being built may change, complexity may rise, and risk may increase”. Therefore, the correct answer is B.
The other options are not acceptable, as they contradict the Scrum principles of empiricism, self-organization, and adaptation.
Reference: The Scrum Guide, section 3. 1. Sprints
Professional Scrum Product Owner I (PSPO I) Learning Path, section 2.2. The Product Owner and the Sprint
B
Explanation:
The Scrum Guide states that “Sprints are the heart of Scrum where ideas are turned into value”. It also states that “Sprints have consistent durations throughout a development effort. A new Sprint starts immediately after the conclusion of the previous Sprint”. Furthermore, it states that “Sprints are limited to one calendar month. When a Sprint’s horizon is too long the definition of what is being built may change, complexity may rise, and risk may increase”. Therefore, the correct answer is B.
The other options are not acceptable, as they contradict the Scrum principles of empiricism, self-organization, and adaptation.
Reference: The Scrum Guide, section 3. 1. Sprints
Professional Scrum Product Owner I (PSPO I) Learning Path, section 2.2. The Product Owner and the Sprint