Practice Free H19-105_V2.0-ENU Exam Online Questions
The UPS5000-A control unit adopts a 1+1 redundant design. When any control unit fails, it can smoothly switch to another control unit, which can effectively prevent the occurrence of single-point failures in the control system and improve the power supply reliability of the system.
- A . True
- B . False
A
For a 79.2+1 parallel UPS system, the maximum load capacity allowed by the system is () times that of a single unit.
The maximum IT power supported by the precision power distribution cabinet of Fusionmodule2000 is ()
- A . 125KW
- B . 145KW
- C . 235KW.
UPS5000-A has reliable, efficient and simple design features. Which of the following statements about UPSS000-A-400/500K are correct? (Multiple choice)
- A . UPS5000-A-400/500K built-in parallel components
- B . UPS5000-A-400/500K supports top airflow
- C . UPS5000-A has two control units
- D . UPS voltage input range 138-485Vac
One of the highlights of the UPS2000-G series products is its high efficiency. It is one of the first UPS in the industry to pass the Energy Star certification.
- A . True
- B . False
Fusionllodule2000 battery entry scenario, how many battery cabinets can be supported at most?
- A . 4
- B . 6
- C . 2
- D . 8
The operating temperature range of FusionModule800 is -20~45 degrees, and the operating temperature range of FusionModule500 is 0~45 degrees
- A . True
- B . False
What type of humidifier does the NetCol 5000-C032H, a row-based intelligent chilled water temperature control product use?
- A . Electrode
- B . Infrared
- C . Wet film
- D . Ultrasound
The capacity management module of the NetEco management system can be connected to a third-party () system to receive equipment change information, automatically generate a change application form, and track the processing process.
- A . NMS
- B . ITSM
- C . CRM
- D . EMS
Which of the following statements about FusionModule2000 routing is incorrect?
- A . There are two wiring troughs on the top of the cabinet, with a total of 4 slots, for 2 strong power lines, one weak power line, and one optical fiber line.
- B . Cross-channel routing can be configured with a routing ladder to cross the top of the fixed skylight for routing
- C . Cross-channel routing through the control skylight
- D . The power distribution cabinet/integrated UPS does not need to be placed at the head of the column
- E . Power distribution cabinet / integrated UPS can be placed outside the module
FusionModule2000 integrated power distribution cabinet has two types of input switches: single-channel MCCB and ATS.
- A . True
- B . False